Building permit is now the construction permit – application process and requirements 2026
Building permit in Finland 2026 – process, cost and time

Finland's building permit became the construction permit in 2025. See when a permit is required, which attachments you need, costs and the 3-month guarantee.
Since the start of 2025, Finland's building permit has been called the construction permit: the new Building Act merged the old permit types into a single permit and abolished the action permit and the notification procedure entirely. This guide shows when a permit is required, how the application proceeds, which attachments are needed and what the permit costs – including the three-month processing-time guarantee in force since the start of 2026, which applies to applications filed complete.
The building permit – now officially the construction permit (rakentamislupa) – is granted by the municipal building control authority, and construction may not begin without it. Finland's Building Act (rakentamislaki, 751/2023), in force from 2025, merged the old permit types: the building permit, the action permit and the notification procedure all disappeared. What remains is a single construction permit, plus the option of first applying for a separate siting permit.
When is a construction permit required?
Under section 42 of the Building Act, a permit is required at least for:
- Any residential building, regardless of size – including a small holiday home
- Any other building of at least 30 m² or 120 m³
- A free-standing canopy of at least 50 m²
- A public structure that at least 5 people can use at the same time
- Any energy well, and any mast or chimney at least 30 m high
A municipal building ordinance can extend the permit requirement to projects with more than minor impact, but it cannot demand a permit for a building the law has declared permit-exempt.
How does the application process work?
The application is filed electronically, in most municipalities through Lupapiste.fi, and needs a named principal designer. The process typically runs: a preliminary meeting with building control, preparation of the plans, consultation of the neighbours, filing with attachments, processing and decision. The decision is announced by public notice, the appeal period is 30 days, and the permit becomes final about 37 days after the decision. Processing times vary: a couple of weeks in small municipalities, up to six months in growth centres.
Two-stage application is new: you can first apply for a siting permit, which settles whether the building can be located as intended – on a planning-need area, for example – and only then the implementation stage. The separate planning-need decision no longer exists. The two-stage route suits situations where you want certainty about the building site before paying for expensive design work.
New for 2026: the three-month processing-time guarantee
From 2026, the municipality must decide the permit within three months of a complete application; exceptionally large and clean-transition projects get six months. If delay is not attributable to the applicant, 20% of the permit fee is refunded for each commencing month. Note the wording: the clock starts only once the application is complete, and missing attachments are the commonest reason processing drags on.
Which attachments does the application need?
- Main drawings: a site plan at 1:200 or 1:500, plus floor plans, sections and elevations at 1:100
- Proof of possession of the building site – the deed of sale or lease agreement
- An energy report and a moisture management report
- A ground investigation and foundation recommendation report
- Neighbour consultations, plus designer and site manager notifications
From the start of 2026, plans are submitted as a building information model or in another machine-readable format. The climate report and carbon footprint limit values came into force at the same time, but detached and other single-family houses are excluded from the climate report obligation.
What does a construction permit cost?
Permit fees are municipal: in Ikaalinen a construction permit costs €300 plus €2/m². For a detached house the fee is typically a few hundred euros – small next to design costs, but the delay compensation is calculated on it.
What happens after the permit?
The permit is not the end but the beginning. Municipal inspections on a small-house site: a kick-off meeting before work starts, attended by the builder, the principal designer, the responsible site manager and building control; a frame-stage inspection; a commissioning inspection, after which you may move in; and a final inspection once the project is complete. Work-stage inspections have shifted to the responsible site manager, who remains compulsory in a small-house project.
Practical tips for a smooth permit process
- Book a preliminary meeting with building control before design work begins
- File the application complete in one go – the processing guarantee does not protect a deficient application
- Handle the neighbour consultations yourself in advance; it speeds up processing
- A house-package supplier, such as a log-house factory, usually provides the permit drawings – confirm who handles the other attachments
- Do not start work before the permit is final
A realistic allowance for design and the permit is one to six months before the first scoop of the excavator.
The permit process is not a mere formality. It forces you to plan the project through to the end before work starts – and careful planning is the cheapest way to avoid mistakes on site.
The most important points
- The building permit and action permit disappeared on 1 January 2025 – there is now one permit, the construction permit.
- A permit is always required for a residential building, for other buildings of at least 30 m² or 120 m³, and for 50 m² canopies.
- From the start of 2026, permits must be decided within 3 months – delays refund 20% of the permit fee per month.
- Applications are filed electronically, and from 2026 plans are submitted in machine-readable format.
- The appeal period is 30 days; the permit becomes final about 37 days after the decision.
- The permit fee is municipal, for example €300 + €2/m² – typically a few hundred euros for a detached house.

Detached houses
Cottages and villas
Sauna huts
Halls
💡Check out the next topic and take your project a step further.
Principal designer in a construction project – role, qualifications and cost 2026
Choosing a plot for your house-building project – 2026 checklist
Energy-efficient house building – requirements and solutions 2026
Local detailed plan – what is it and why does it matter for building?
U-value: a guide to structural energy efficiency and thermal insulation
Wastewater systems in rural areas: requirements and prices 2026
Building permit is now the construction permit – application process and requirements 2026
Ground source heating for a house – price, installation and savings 2026
Ground investigation: 2026 price, contents and foundation recommendation
Mechanical ventilation with heat recovery: how to secure good indoor air
CLT construction: cross-laminated timber in Finland in 2026
Smart home 2026: how home automation cuts your electricity bill
A building's carbon footprint – climate report and limit values 2026
Construction budget: a guide to drawing up a cost estimate 2026
Building without a permit – what can you build in Finland in 2026?
Building close to the neighbour's boundary – distances and rules 2026
Log house 2026: modern log building and healthy living
Round log: a guide to building a traditional, atmospheric home
Choosing a house package 2026: delivery contents, prices and comparison
Log types compared: laminated, solid or non-settling log?
Foundation selection guide 2026: the right foundation for a detached house
Moisture management during construction: requirements and practice 2026
Ground source or air-to-water heat pump? A 2026 comparison
Can you build on the shore? Finland's shoreline building rules 2026
Plot parcelling in Finland 2026 – cost, stages and duration
Prefabricated hall: what's included, erection time and price 2026
Building an unheated garage: structure, ventilation and price 2026
Garage interior: 10 ideas for storage, flooring and lighting
Contact us and request a quote
Leave your information and our expert will contact you shortly. Let's discuss together how we can best implement your construction project.